Early-winter sunlight falls across a grassy opening among bare trees, copper beech leaves and mossy rocks in a Westchester-like woodland.

Where Chappaqua's ChapLine Trail Stands This Winter

November 26, 2026

On paper, the ChapLine starts at a small trailhead on Roaring Brook Road, near the entrances to Horace Greeley High School and Chappaqua Crossing. It crosses a gorge on a truss bridge and runs south through woods, over wooden boardwalks and wetland stream crossings. It ends at Bischoff Avenue and North Greeley Avenue, where an existing sidewalk continues into downtown Chappaqua. The Town of New Castle describes the whole route as a 1.7-mile multi-use path for walking, biking and running.

No one can walk it yet. The current project schedule puts the start of construction in fall 2027 or winter 2028. The trail is planned in three phases, and each phase can open on its own, so the trail will reach the public one section at a time. The first section is the wooded north end near the high school. The trail also mostly follows a corridor the county cleared long ago, which is why a path that has been discussed for nearly a decade is finally moving through state and federal review.

The route follows a line the county already cleared

Route 117 is the obvious way to get between the hamlet and Chappaqua Crossing, and the ChapLine is designed to keep walkers and cyclists off it. The path follows a Westchester County sewer trunk line through the woods. New Castle Supervisor Victoria Tipp told The Inside Press in August 2025 that the route stays off private property and Chappaqua Central School District land.

"This would not be an original disturbance of the area," Tipp told The Inside Press in the same interview. "The area has already been cleared and disturbed by the Westchester County sewer trunk line."

The town's revised 2024 feasibility study describes the same approach. Its preferred route runs beside Metro-North property west of the Chestnut Oaks condominiums, then uses town property and parts of the sewer corridor, steering around private and school parcels and keeping wetland impacts low. The corridor has its own small streams, including Chappaqua Brook and Shadow Brook. That is why the design uses boardwalk over wet ground instead of grading a path through it.

What the walk will look like, north to south

If you know the woods behind Chestnut Oaks and the stretch along Roaring Brook Road, you can picture most of this. Here is the route as the 2024 study and Tipp's 2025 description lay it out, from the high school end down to the hamlet:

  1. Roaring Brook Road trailhead. The study's plan has 20 parking spaces, two of them ADA spaces, plus lighting, signage, an orientation kiosk, a bike repair station, a bottle-fill station, benches and bike racks.
  2. The gorge crossing. Near the north end, a pedestrian truss bridge spans an existing gorge and connects the trail to the trailhead.
  3. The Town Bird Sanctuary. The study describes this protected area as town-owned. Tipp placed it near Lawrence Farms South.
  4. The Metro-North easement. The trail picks up the railroad easement at the north end of the Chestnut Oaks property and follows it south.
  5. Bischoff Avenue and North Greeley Avenue. The trail meets the existing sidewalk here, and the sidewalk continues toward downtown and the train station area.

The trail itself will be asphalt, with wooden boardwalk sections raised over wetlands and stream crossings. Tipp also mentioned bike sharing, benches, water-fill stations and signage.

Why the woods near the high school come first

The trail is built in phases, which shapes the order of the list above. In August 2025, Tipp said the first construction phase would likely start on Roaring Brook Road and run to the bird sanctuary near Lawrence Farms South. Phase two would continue to the north end of the Metro-North easement at Chestnut Oaks. The final phase would run through the south end of the railroad easement to Bischoff and North Greeley.

According to Tipp, the phases are independent of each other, so the public could use each finished section before the next one is built. In that plan, the first section to open is the stretch with the parking lot, the bridge and the sanctuary. The downtown connection comes last.

The project page calls its schedule preliminary, and this winter the draft design is with state and federal reviewers, with the final design report scheduled for March or April 2027.

The project page sets out who the path is meant to serve: Chappaqua Crossing, Greeley and the downtown, linked for recreation, commuting and getting around town. In August 2025, Tipp told The Inside Press that about 6,500 people live in the immediate area of the Chappaqua hamlet. Chappaqua Crossing adds 91 townhomes and 64 residential units in the cupola building. She predicted the finished trail will have "a truly transformative impact" on the town and said it could get more people walking from one side of the hamlet to the other.

How the money came together

The cost has risen as the plan aged. The feasibility study's preliminary total was $10,089,765. That figure came from a December 2020 estimate with an inflation allowance through 2023. By August 2025, The Inside Press reported the estimate at roughly $11 million, with an updated figure to come from the design consultant.

The largest piece is a $5 million state Transportation Alternatives Program grant, which The Examiner News reported in January 2025. With the town's own contribution and an earlier $500,000 Climate Smart Communities grant, New Castle had set aside $7.25 million for the ChapLine as of August 2025, The Inside Press reported.

The grant application carried letters of support from State Senator Peter Harckham, Assemblyman Chris Burdick, County Executive Ken Jenkins, Board of Legislators Chair Vedat Gashi, the Chappaqua Central School District, Teatown Lake Reservation and the Saw Mill River Audubon Society. "We worked very hard to get this," Burdick told The Inside Press.

Tipp expected the gap to shrink as the design matures. "More grants are likely once you have shovel-ready projects, and this will be more than shovel-ready," she told The Inside Press.

The calendar from here

The design consultant keeps the working schedule on the ChapLine project page. The page lists project start, site inventory, alternatives review and the preferred alignment as complete, covering September 2025 through April 2026. It also listed a Town Board update for November 10, 2026. Here is what comes next, as the page currently shows it:

Step Scheduled timing
NYSDOT and FHWA review of the draft design November 2026 to February 2027, three months minimum
Town Board update January or February 2027
Public Information Meeting on the preferred alignment February 2027
Town Board update March 2027
Final design and final design report March or April 2027
Final design approval from NYSDOT and FHWA May 2027
Final construction documents submitted for state review and bidding Fall 2027
Construction start Fall 2027 or winter 2028
Construction complete 2028, date to be determined

The project page says the schedule may shift with agency review periods, permitting, funding requirements and weather, and that the page will be updated as dates change. For residents, the February 2027 Public Information Meeting is the date to note. The schedule describes it as the session where the project's progress and preferred alignment are presented to the public.

If you live near Roaring Brook Road, Lawrence Farms South, Chestnut Oaks or the North Greeley end, that meeting is where you will see how the path meets your part of town. If your household moves between Greeley, Chappaqua Crossing and downtown every day, it will show which piece of the walk you can expect to use first. For more on how the hamlet and Chappaqua Crossing fit together, our Chappaqua neighborhood guide covers the area around the route.

A new path can change how a street feels to live on, especially at the trailhead end and along the stretch beside Chestnut Oaks. If you own near the ChapLine route and want to talk through what the trail could mean for your home, or you are looking for a place within walking distance of it, Marcie Nolletti is glad to go over the details with you. Let's Connect.